| Bednayel 15 MWp PV Plant | 2018 | Bednayel, Lebanon | Manalco | Photovoltaic | 15 MWp PV plant connected by a 6 km overhead line to the EDL substation | Realized Connection Study and design of the MV overhead line connection |
Project Background & Objectives
Project Challenges
Transmitting 15 MWp of volatile solar power over a long 6 km overhead transmission corridor introduces significant electrical and structural engineering hurdles. PDP Energy had to navigate severe technical complexities, including mitigating substantial voltage drop risks over the long distance, calculating line impedance, and designing robust thermal capacity parameters for the conductors. Additionally, interfacing a large private generation asset with an unstable public utility grid required engineering complex protection coordination schemes and transient stability modeling to prevent reverse power flows or grid trips at the EDL substation.
Project Outcomes
Operating as the specialized grid-integration engineer, PDP Energy successfully delivered the complete connection study and engineering design package for the medium-voltage overhead line. The project effectively established a highly accurate and compliant technical model for utility-scale solar evacuation in the region. By delivering flawless electrical transmission blueprints, PDP Energy cleared the way for the secure deployment of the 15 MWp solar asset, guaranteeing safe, high-efficiency power delivery across the 6 km span into the national grid.